Building the Future of American Steel: Gary Works 2026 Investments by the Numbers


Building the Future of American Steel
U.S. Steel is putting hundreds of millions of dollars back into Gary Works. Here is what is happening at North America’s largest integrated steel mill, and what it means for the maintenance teams who keep it running.
Gary Works from the air, July 2025. Photo: “Aerial view of U.S. Steel Works in Gary, IN” by Grešla, CC BY-SA 4.0, cropped.
For more than a century, Gary Works has anchored the south shore of Lake Michigan. In 2026 it is in the middle of its biggest reinvestment in years: a rebuilt blast furnace, a hot strip mill upgrade in the pipeline and a tin mill coming back to life.
Gary Works is U.S. Steel’s largest manufacturing plant, with 7.5 million net tons of annual raw steelmaking capability, four blast furnaces and an 84-inch hot strip mill. After Nippon Steel completed its purchase of U.S. Steel in 2025, the company laid out a growth plan that targets about $14 billion of U.S. growth capital, with $11 billion to be invested by the end of 2028. Gary Works is one of the first places that money is showing up.
Gary Works by the Numbers
Where the Money Is Going
Near-term Gary Works projects
Announced capital, in millions of dollars
The bigger picture
U.S. Steel growth plan
About $11 billion of the roughly $14 billion U.S. growth plan is scheduled to be invested by the end of 2028.
More Than a Century on the Lakefront
1918
2025Timeline: From Sand Dunes to 2027
- 1906U.S. Steel begins building its new mill on the dunes of Lake Michigan’s south shore, founding the city of Gary.
- 1908Gary Works begins operating; the first iron ore shipment arrives in June.
- 1963Calumet Chicago Company is founded to serve the region’s mills, plants and shops.
- 2022Most Gary tin operations are idled at the end of the year.
- 2025Nippon Steel completes its purchase of U.S. Steel. In November, U.S. Steel announces a growth plan of about $14 billion.
- May–Aug 2026Blast Furnace #14 is taken down for a roughly 100-day reline, the largest furnace in U.S. Steel’s footprint.
- September 2026Blast Furnace #14 returns to service after more than 1 million labor hours.
- Early 2027Gary Tin Mill restart expected, supporting about 225 jobs. The hot strip mill and steel shop upgrades will follow once state permits are in place.
What It Means on the Plant Floor
Big capital projects get the headlines, but every restart, reline and upgrade lands on the maintenance department. U.S. Steel says the Tin Mill restart budget is mainly for equipment inspections, maintenance and materials. That is the kind of work where clean parts and reliable lifting equipment make the difference.
Restarts start with teardown
Equipment that sat idle has to be opened, inspected and cleaned before it runs again. Grease and mill scale have to come off before anyone can judge wear.
Outages run on the clock
A 100-day reline leaves no slack. Loading a washer and walking away beats a crew hand-scrubbing parts in a solvent tank.
Safer, solvent-free cleaning
Heated aqueous washers use water-based detergent instead of flammable solvent, and the wastewater is pumped out and handled for you.
Lifting you can trust
Mills, rail shops and heavy equipment crews depend on industrial and railroad jacks that are inspected, rebuilt and tested.
Real Steel Mill Parts, Before and After
These are real parts from local plants, cleaned in Cuda aqueous parts washers serviced by Calumet Chicago Company.
See more results on our See it in action page.
How Calumet Chicago Helps Keep Industry Running
Since 1963, Calumet Chicago Company has supported Northwest Indiana’s mills, plants and shops from Highland, Indiana. We are an authorized Cuda parts washer distributor and a repair center for industrial and railroad jacks.
Cleaner parts. Less manual labor. More productive maintenance.
Stop Scrubbing… Start Loading!
Questions and Answers
What is U.S. Steel investing in Gary Works?
Near-term projects include the completed $350 million reline of Blast Furnace #14, about $200 million in hot strip mill and steel shop upgrades, and a $15–20 million restart of the Gary Tin Mill. Together they come to roughly $565–570 million.
When will the Gary Tin Mill restart?
U.S. Steel expects the restart in early 2027, subject to maintenance, materials and workforce readiness. It is expected to support about 225 jobs.
Is Blast Furnace #14 back in service?
Yes. U.S. Steel returned Blast Furnace #14 to service in September 2026 after a reline that took more than 1 million labor hours.
Who services Cuda parts washers near Gary, Indiana?
Calumet Chicago Company sells, leases and services Cuda aqueous parts washers from Highland, Indiana, about 15 minutes from Gary. Call (708) 474-2343 or visit our Northwest Indiana service page.
Sources
- U.S. Steel: Locations, Gary Works
- U.S. Steel: Unveils New Era of Growth (November 4, 2025)
- U.S. Steel: Completes $350 Million Gary Works Blast Furnace #14 Reline (September 3, 2026)
- U.S. Steel: Forging Our Future, Progress Overview
- U.S. Steel: Announces Plans to Restart Gary Tin Mill
- The Times of Northwest Indiana: US Steel investing up to $570 million in Gary Works (November 10, 2026)
- Wikipedia: Gary Works history
Calumet Chicago Company is an independent industrial supplier. This article is based on public announcements and is not affiliated with or endorsed by U.S. Steel or Nippon Steel.